Participant105. No 1 & 2 Machine House, 11/11/21.
Work erecting both machines well advanced. Trolley wires are in place along the crane rail to power the electric bridge crane.
Attachments:
29th July 2021 at 09:13 #1395Artless Bodger
Participant106. Conveyor, 16/12/21.
Attachments:
29th July 2021 at 09:14 #1397Artless Bodger
Participant107. Conveyor, 14/12/21.
Attachments:
29th July 2021 at 09:23 #1399Artless Bodger
Participant108. General View, 31/12/21.
Taken presumably from the top of the water tower, similar to earlier views. At this time the temporary standard gauge siding has been repositioned to the further opening into the turbine house for the delivery of equiment. The two gable walls, one concrete, the other corrugated iron would become internal walls when the mill was extended in 1923/24 with the installation of 3 and 4 machines, the beaterfloor extension being the first part of the kraft beaterfloor. The corrugated iron gable all would eventually be replaced with concrete when the turbine house was extended and in the 70s had a small opening about 2′ square with a metal door through which you could look down into the turbine house.
Attachments:
29th July 2021 at 09:36 #1401Artless Bodger
Participant29th July 2021 at 09:37 #1403Artless Bodger
Participant110. Salle, 6/1/22.
Attachments:
29th July 2021 at 10:28 #1405Artless Bodger
Participant111. Coal Bunkers and Wharf Road, 1/1/22.
Inset rails for the dockside cranes being installed, stanchions and trolley wires to power the cranes in place along the upper wall of the bunkers.
Attachments:
12th August 2021 at 13:50 #1407Artless Bodger
Participant112. Water Tower, 10/2/22.
Looking towards the river, this is the original water tower, later replaced by the 6 legged, taller tower which had REEDS in large red letters on its tank, demolished with explosives in the late 1980s.
Attachments:
12th August 2021 at 13:52 #1409Artless Bodger
Participant113. Salle, 6/1/22.
The machine house end wall visible upper right. Tracks for a bridge crane on top of double stanchions in the centre bay.
12th August 2021 at 14:01 #1410Artless Bodger
ParticipantResized image 113
Attachments:
12th August 2021 at 14:29 #1412Artless Bodger
Participant12th August 2021 at 14:45 #1414Artless Bodger
Participant115. Machine House, 19/3/22.
Attachments:
12th August 2021 at 14:47 #1416Artless Bodger
Participant116. Economisers, 24/3/22.
The arrangement of gears on the top is to raise and lower the scrappers on the outside of the water tubes, to clean off soot.
Attachments:
12th August 2021 at 14:53 #1418Artless Bodger
Participant117. No 2 Annexe, 19/3/22.
Attachments:
12th August 2021 at 15:15 #1420Artless Bodger
Participant118. No 2 Machine Calenders, 7/5/22.