Forum Replies Created
-
AuthorPosts
-
Artless Bodger
Participant118. No 2 Machine Calenders, 7/5/22.
Attachments:
Artless Bodger
Participant117. No 2 Annexe, 19/3/22.
Attachments:
Artless Bodger
Participant116. Economisers, 24/3/22.
The arrangement of gears on the top is to raise and lower the scrappers on the outside of the water tubes, to clean off soot.
Attachments:
Artless Bodger
Participant115. Machine House, 19/3/22.
Attachments:
Artless Bodger
ParticipantArtless Bodger
ParticipantResized image 113
Attachments:
Artless Bodger
Participant113. Salle, 6/1/22.
The machine house end wall visible upper right. Tracks for a bridge crane on top of double stanchions in the centre bay.
Artless Bodger
Participant112. Water Tower, 10/2/22.
Looking towards the river, this is the original water tower, later replaced by the 6 legged, taller tower which had REEDS in large red letters on its tank, demolished with explosives in the late 1980s.
Attachments:
Artless Bodger
Participant111. Coal Bunkers and Wharf Road, 1/1/22.
Inset rails for the dockside cranes being installed, stanchions and trolley wires to power the cranes in place along the upper wall of the bunkers.
Attachments:
Artless Bodger
Participant110. Salle, 6/1/22.
Attachments:
Artless Bodger
ParticipantArtless Bodger
Participant108. General View, 31/12/21.
Taken presumably from the top of the water tower, similar to earlier views. At this time the temporary standard gauge siding has been repositioned to the further opening into the turbine house for the delivery of equiment. The two gable walls, one concrete, the other corrugated iron would become internal walls when the mill was extended in 1923/24 with the installation of 3 and 4 machines, the beaterfloor extension being the first part of the kraft beaterfloor. The corrugated iron gable all would eventually be replaced with concrete when the turbine house was extended and in the 70s had a small opening about 2′ square with a metal door through which you could look down into the turbine house.
Attachments:
Artless Bodger
Participant107. Conveyor, 14/12/21.
Attachments:
Artless Bodger
Participant106. Conveyor, 16/12/21.
Attachments:
Artless Bodger
Participant105. No 1 & 2 Machine House, 11/11/21.
Work erecting both machines well advanced. Trolley wires are in place along the crane rail to power the electric bridge crane.
Attachments:
-
AuthorPosts